Chico Project Phase 1B: Ladera Rd. and Atrisco Vista Blvd Sanitary Sewer Improvements

Project Scope: This project includes installation of approximately 1240 LF of new sanitary sewer pipe and manholes along the future Ladera Rd from intersection of Comfort Way to Atrisco Vista and installation of 2,240 LF along Atrisco Vista Blvd from Ladera Rd. going south and tie into an existing sanitary sewer manhole.

Funding: This project is comprised of Bernalillo County District 1 Bonds.

General Project Information

Status | Bidding
Project Engineer | Leila Momenzadeh P.E.
Estimated Design Cost | $51,160
Design Start | May 2020
Design Completion | September 2020
Design Consultant | Bohannan Huston Inc
Anticipated Construction Start |November 2020
Anticipated Construction Completion | December 2020
Estimated Construction Cost | $650,000.00

Project Contact Information:

Project Engineer | Leila Momenzadeh

Office Phone | (505) 224-2124
Cell Phone | (505) 252-2837
E-mail | lmomenzadeh@bernco.gov

back to list